Enchantress Refit

Enchantress underwent a major refit in the 2008/2009 period and since returning from the 2009-2011 Blue Water Rally it has been undergoing another refit.

2011/2014 Refit Details


2008/2009 Refit

Hull:

  • Sandblasting and epoxy painting of the keel
  • Removal of all antifouling and application of 7 coats of Gelshield 200 Osmosis protection on hull and keel.
  • Removal and inspection of 3-4 keel bolts
  • Removal and refurbish rudder and fittings
  • Renewal of all tank breathers
  • Remove and reseal all stantions and cleats

Rigging/Sails

  • Replacement of all stainless steel standing rigging
  • Replacement of guardrails
  • Replace jackstays
  • Replacement of Genoa and Staysail furling systems
  • Overhaul of the Mainsail in-mast furling system
  • Add mast climbing steps to mast
  • Add 2nd Spinnaker system
  • Fit new winches and rope organiser system for mainsail reefing
  • Add additional lifeline attachments
  • Reseal Chainplates & check bolts
  • Replace most halyards/sheets
  • Buy backup mainsail
  • Replace Staysail
  • Buy staysail hank sleeve for storm sail

Safety Equipment:

  • Fit Man Overboard Tracking system from Pinball & service MOB Watches
  • Replace lifebuoy & MOB retrieval system
  • Buy new GPS EPIRB  & service old EPIRB
  • Service Liferaft
  • Replace Danbuoy
  • Buy & Build  Storm Sea Drogue system
  • Replace fire extinguishers
  • Replace lee cloths
  • Add 2nd manual bilge pump
  • Replace electric bilge pump
  • Fit wooden plugs at all seacocks
  • Buy new lifejackets

Deck/External Equipment:

  • Refurbish all hatches with new perspex and seals
  • Repair sealing in teak deck
  • Replace dorade air vents with mushroom vents
  • Replace cockpit instrument panel
  • Repair and reproof cockpit cover
  • Strenthen Granny rails with proper bolts through deck
  • Replace forward  electric windlasses
  • Replace chain and anchor with system sized to best practice.
  • Fit Pinball's Spade anchor as 2nd anchor.
  • Fit 2nd bow roller & Samson post for mooring
  • Strengthen Anchor locker
  • Replace steering cables and conduits & service overall system
  • Transfer WindPilot system from Pinball
  • Upgrade electric autopilot system

Instruments:

  • Replace Navtex weather system
  • Replace VHF system with dual station DSC model
  • Transfer Chart Plotter from Pinball
  • Fit Instrument Pod at wheel position
  • Replace SSB & add Pactor modem
  • Add AIS boat identification system
  • Fit GPS system from Pinball
  • Fit Forward Looking Sonar system
  • Replace depth and speed systems
  • Replace boat PC

Electrical systems:

  • Replace tricolour with LED system
  • Fit Strobe light for maximum visibility
  • Overhaul navigation lights
  • Fit solar panels
  • Fit Wind generator
  • Fit aqua generator from Pinball
  • Replace power distribution fuse panel with modern breaker system & overhaul wiring panel arrangement
  • Fit DC-AC Inverter
  • Replace old batteries & secure down
  • Replace battery charger
  • Fit Adverc battery control system and battery monitor system
  • Fit cockpit lights
  • Replace saloon light with LCD bulbs
  • Fit new Anode system with associated bonding

Other systems:

  • Overhaul engine
  • Buy spare engine alternator & starter
  • Replace propeller with 3 blade folding propeller
  • Replace Deep Sea seal
  • Overhaul engine compartment insulation
  • Replace cooker
  • Replace complete gas system & build gas locker
  • Replace stern toilet
  • Make/fit hatch covers/fly screens
  • Overhaul cabin steps
  • Overhaul manual fresh/sea water pumps & replace all pipes

2008 REFIT PICTURES

The original name of the boat revealed after much sanding. Branco was a famous Brasilian footballer.

The hull after the antifouling has been scraped off.

Minor surface cracks had to be filled before the Osmosis protection could be added.

3 keelbolts removed for checking.

Starting the sandblasting of the keel.

Nearly finished the sandblasting.

The first coat of Epoxy being added immediately after sandblasting.

Making sure that all parts of the keel are covered.

The pitting on the keel is filled before the Gelshield is added.

The first of 7 coats of Gelshield 200.

Another coat done.

The hull ready for antifouling.

The rudder with about 10 coats of Gelshield 200.

The new antifouling added.

The new antifouling added.

Mast and Rigging building the 2 new furling headsail systems.

The new Navpod with the Chart Plotter, AutoPilot and VHF remote control.

New covering & fittings on steps to make them safer.

Susan doing her artistic bit.

A tight squeeze in DRB's shed.

Safely out of the shed after a 6 week stint.

Enchantress looking good.

Launched and waiting for the mast.

Now looking like a boat with the mast fitted.


 

 

This page was last modified on: January 31, 2013